View Details
| Bid Classification: |
Construction
|
|---|---|
| Bid Type: | RFT |
| Bid Number: | 10045293 |
| Bid Name: | RFT Humber Bay Park East (HBPE) Pump Station Restoration |
| Bid Status: | Open |
| Bid Closing Date: | Fri Nov 13, 2026 12:00:00 PM (EST) |
| Question Deadline: | Fri Nov 6, 2026 12:00:00 PM (EST) |
| Duration in months: | 6 |
| Negotiation Type: | Refer to project document |
| Condition for Participation: | Refer to project document |
| Electronic Auctions: | Not Applicable |
| Language for Bid Submissions: | English unless specified in the bid document |
| Submission Type: | Online Submissions Only |
| Submission Address: | Online Submissions Only |
| Public Opening: | No |
| Description: |
WORK OF THIS CONTRACT 1. The pump station has extensive damage due to flooding during a period of non-operation. As a result, all electrical and mechanical equipment must be removed and replaced. In addition, all electrical, conduit, and wiring systems must be replaced due to water damage and corrosion in and around the electrical equipment. 2. The Work includes furnishing all labour, materials, equipment, and incidentals required to replace all equipment installed in the Humber Bay Park East (HBPE) Transfer Pump Station to return the station to full operation. Equipment to be replaced and commissioned includes, but is not limited to the following:
3. This work includes the supply of an inlet extension steel pipe into Lake Ontario to support the pump station. As part of the project, TRCA requires a qualified Contractor to fabricate, supply, deliver and unload an inlet extension steel pipe, including all components, to the Project site. The Intention is that the work will be staged such that the Contractor shall complete most of their scope of work and before testing and commissioning demobilize from the site to allow for TRCA to install the pipe. Upon Completion the Contractor shall remobilize to complete the scope as well as perform all testing and commissioning. 4. ALL WORK under this Contract which is located within the pump chamber or wet well is deemed to be Confined Spaced under the Ontario Construction Regulations. The Contractor shall complete and submit a detailed site-specific Working in a Confined Space plan including recovery plan and Job Hazard Analysis. All pricing submitted must be inclusive of all additional measures which may be required to facilitate working under these conditions. |
| Bid Document Access: | Bid document preview, bid opportunity, and award notices are available on the site free of charge. Suppliers are not required to register for a bid opportunity prior to previewing unsecured bid documents. Please note, some documents may be secured and you will be required to register for the bid to download and view the documents. To download secured documents and/or to participate in this opportunity, you will need to have a subscription plan or buy Pay-Per-Bid access for this opportunity (available if you don't have an active subscription). |
| Trade Agreements: |
Show Trade Agreements [+]
Canada-European Union Comprehensive Economic and Trade Agreement (CETA)
Canadian Free Trade Agreement (CFTA) |
| Categories: |
Show Categories [+]
|
Meeting Locations
The following are the meeting times and locations for the bid: